DUNG QUAT REFINERY PROJECT
- THE OWNER: PETRO VIET NAM
- MAIN CONTRACTOR: TECHNIP CONSORTIUM
- SUB CONTRACTOR: PHA DIN CORPORATION
- CONCRETE: 120.000 M3
POURING CONCRETE DATE 30/08/2007 - 2,650 M3 WITHIN 12H (PHA DIN 1,350 M3)
 
|
DUNG QUAT REFINERY PROJECT (CERTIFICATE)
 
|
VINASHIN DUNG QUAT PROJECT |
DOOSAN VINA PLANT IN DUNG QUAT PROJECT |
  |
PROPYLEN DUNG QUAT PROJECT |
CHU LAI GLASS PROJECT |
  |
QUANG LIEN STEEL PROJECT
SUPPLY CONCRETE DATE 3th SEPTEMBER 2008 (PHA DIN SUPPLY 2.000 M3)
 
|
PHU MY 2.2 BOT PROJECT
- MAIN CONTRACTOR: EIFFAGE INTERNATIONAL
- SUB - CONTRACTOR: GENERAL COMPANY OF CONSTRUCTION No. 1
- THE CONCRETE SUPPLIER AND CONCRETE PUMPING
- SUB - CONTRACTOR: PHA DIN CORPORATION
- TIME: 10/2002 - 06/2004
- QUANTITY: 42.000 M3 CONCRETE
PHU MY COLD ROLLING STEEL MILL COMPLEX:
CIVIL WORK No.22: FOUNDATIONS OF MAIN EQUIPMENTS AND MAIN BUILDING
- MAIN CONTRACTOR: GENERAL COMPANY OF CONSTRUCTION AND MECHANISM
- SUB - CONTRACTOR: PHA DIN CORPORATION
- TIME: 12/2003 - 12/2004
- QUANTITY: 45.000 M3 CONCRETE, 13.000 M REINFORCED, 2.100 TONS STEEL, 30.000 M2 FORM WORK.
 
CIVIL WORK CW2:
CIVIL WORK FOR HEAD WORK OF DAI NINH HYDRO POWER PROJECT
- MAIN CONTRACTOR: HAZAMA CORPORATION
- THE CONCRETE SUPPLIER AND CONCRETE PUMPING
- SUB CONTRACTOR: PHA DIN CORPORATION
- TIME: 04/2004 - 06/2006
- QUANTITY: 115.000 M3 CONCRETE.
 
SP - PSA INTERNATIONAL PORT PROJECT
- THE OWNER: SP - PSA COMPANY LIMITED
- MAIN CONTRACTOR: PENTA - OCEAN CONSTRUCTION
- SUB CONTRACTOR: PHA DIN CORPORATION
- QUANTITY CONCRETE: 20.000 M3, CBGM: 40.000 M3
CONCRETE FOR CONTAINER STACKING YARD 20/2/2009
 
|
HOA SEN COLD ROLLING STELL MILL COMPLEX
- THE OWNER: HOA SEN GROUP
- CONTRACTOR: IDICO, KIM NGUON...
- SUB CONTRACTOR: PHA DIN CORPORATION
- QUANTITY CONCRETE: 60.000 M3.
SUPPLY CONCRETE JANUARY 2010
 
|
PHUONG BAC HOTEL PROJECT FEBRUARY 2010
PHADINBATCHING PLANT IN PHU THO PROVINCE BIO ETHANOL PROJECT
- THE OWNER: PVB
- CONTRACTOR: PVC
- SUB CONTRACTOR: PHA DIN CORPORATION
- QUANTITY CONCRETE: 60.000 M3.

|